Tel:
966 12 684 8046
966 12 684 8959

 
  Fax:
966 12 640 5622
 
  AFS
OEJDYKYX
 
  http://www.sans.com.sa
 
  E-mail:
aim@sans.com.sa
 
       
 
KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
SAUDI AIR NAVIGATION SERVICES
AERONAUTICAL INFORMATION MANAGEMENT
P. O. BOX 929, JEDDAH - 21421

     
  AIP
SUP

AIP SUP 52/25
28 NOV 2025
 
     
   

OEJN — JEDDAH / KING ABDULAZIZ INTL AIRPORT – Royal Helipads Rehabilitation Project – Apron 8

1 .Introduction:

This AIP supplement provides information regarding the phased rehabilitation works for Royal Helipads at Apron 8 at King Abdulaziz International Airport (OEJN). The project includes upgrading helipad pavement, markings, lighting system and safety area to enhance operational safety.

2 .Timeframe for the installation activities:

The installation activities of Royal Terminal Helipads rehabilitation works will be carried out in multiple phases to complete civil and electrical works. These activities are divided as follows:
 
Project Phases Activity Duration Consequence Remark
Phase 1 Electrical room construction (Civil and structural works, MEP & finishes) +12 weeks
  • Helipads (H1, H2 & H3) and stands (8-1 and 8-1A) will be closed throughout the project duration via NOTAM.
  • Construction works area will be isolated from airside (Apron 8) Ops.
Phase 2 Duct bank works from electrical room to manhole 03 (Excavate, install ducts, concrete cover and backfill) +10 weeks
Phase 3 manhole 03 to helipads (Excavate, install ducts, concrete cover, backfill and level) +7 weeks
Phase 4 Lighting system installation (Install lights, run cables and connect to electrical room) +9 weeks
Phase 5 Helipads surface & Markings (Repainting, leveling and cleaning) +3 weeks
Phase 6 Test commissioning +2 weeks    

3 .Activation of the AIP supplement:

Trigger NOTAM will be issued in accordance with AIRAC procedure.

4 .Replacement or cancellation of the AIP SUP:

Any significant change in the current information would be notified by replacement AIP Supplement.  

This AIP Supplement will remain effective until further notice, and NOTAM will be issued to announce the cancellation of this AIP SUP. 

5 .Inquiries:

For any inquiries, please contact:
Aerodrome / SANS CONTACT DETAILS
Jeddah TWR Name: JED Tower 
Email: jedtwr@sans.com.sa 
Aerodrome Operator (JEDCO) Name: Adil Abdo 
Email: aabdo@jeddahairports.sa  
Aerodrome Operator (JEDCO) Name: Moataz Faraj  
Email: mafaraj@jeddahairports.sa  

-END-

OEJN AD AIP SUP 52-25