OEJN — JEDDAH / KING ABDULAZIZ INTL AIRPORT – Royal Helipads Rehabilitation Project – Apron 8
|
|
|
This AIP supplement provides information regarding the phased rehabilitation works for Royal Helipads at Apron 8 at King Abdulaziz International Airport (OEJN). The project includes upgrading helipad pavement, markings, lighting system and safety area to enhance operational safety.
|
2 .Timeframe for the installation activities:
|
The installation activities of Royal Terminal Helipads rehabilitation works will be carried out in multiple phases to complete civil and electrical works. These activities are divided as follows:
|
Project Phases
|
Activity |
Duration |
Consequence |
Remark |
|
Phase 1
|
Electrical room construction (Civil and structural works, MEP & finishes) |
+12 weeks |
-
Helipads (H1, H2 & H3) and stands (8-1 and 8-1A) will be closed throughout the project duration via NOTAM.
|
-
Construction works area will be isolated from airside (Apron 8) Ops.
|
|
Phase 2
|
Duct bank works from electrical room to manhole 03 (Excavate, install ducts, concrete cover and backfill) |
+10 weeks |
|
Phase 3
|
manhole 03 to helipads (Excavate, install ducts, concrete cover, backfill and level) |
+7 weeks |
|
Phase 4
|
Lighting system installation (Install lights, run cables and connect to electrical room) |
+9 weeks |
|
Phase 5
|
Helipads surface & Markings (Repainting, leveling and cleaning) |
+3 weeks |
|
Phase 6
|
Test commissioning |
+2 weeks |
|
|
|
3 .Activation of the AIP supplement:
|
Trigger NOTAM will be issued in accordance with AIRAC procedure.
|
4 .Replacement or cancellation of the AIP SUP:
|
Any significant change in the current information would be notified by replacement AIP Supplement.
This AIP Supplement will remain effective until further notice, and NOTAM will be issued to announce the cancellation of this AIP SUP.
|
|
|
For any inquiries, please contact:
|
Aerodrome / SANS
|
CONTACT DETAILS
|
|
Jeddah TWR
|
Name: JED Tower
Email:
jedtwr@sans.com.sa
|
|
Aerodrome Operator (JEDCO)
|
Name: Adil Abdo
Email:
aabdo@jeddahairports.sa
|
|
Aerodrome Operator (JEDCO)
|
Name: Moataz Faraj
Email:
mafaraj@jeddahairports.sa
|
-END-
|
|
|
OEJN AD AIP SUP 52-25
|